ECDA Activities
Pond was contracted by ExxonMobil to conduct an external corrosion direct assessment (ECDA) on the Beaumont to DuPont Hydrogen Line MR-27, which spans 3.11 miles (16,431 feet) of 10-inch hydrogen gas transmission pipeline in Beaumont, Texas.

The four-step ECDA process includes pre-assessment, indirect inspection, direct examination, and post-assessment. This indicates a thorough assessment and maintenance process aimed at ensuring the continued safe operation of the hydrogen gas transmission pipeline.
Project Photos
CLIENT
ExxonMobil
LOCATION
Beaumont, Texas
Similar Projects
We earn the trust that sets us apart.
TOP